SE concluded pressure test on Mochovce third nuclear unit

Zdieľať na Facebooku Zdieľať Odoslať na WhatsApp Odoslať Diskusia
Atómová elektráreň Mochovce SE
Atómová elektráreň Mochovce. Foto: SE

The completion of the third and fourth nuclear unit in Mochovce took another significant step. Slovenske Elektrarne, which is in charge of the completion of the nuclear units in Mochovce, successfully tested six steam generators and pipes connected to the reactor at the third block. The pressure test is one of the crucial conditions for launching the nuclear power plant. According to the latest data, the third block is completed to 94% and the fourth to 80%. After this pressure test, Slovenske Elektrarne will continue preparations of the components and the third block system for another major milestone – cold hydrostatic test.

Full story in Slovak: Elektrárne vykonali tlakovú skúšku na treťom jadrovom mochoveckom bloku

Zdieľať na Facebooku Zdieľať Odoslať na WhatsApp Odoslať Diskusia
Firmy a inštitúcie SE Slovenské elektrárne